Comments
- The Current State Interim Report is still in progress in order to incorporate the data received from the Technology Satisfaction and
Needs Survey, conducted by Survey Research. However, we continue to plan to present the draft plan to the campus community
during the fall quarter for implementation in early 2003.
Problems/Issues/Concerns
- Not Applicable
Tasks Planned for 06/01/02 through 06/30/02
- Finalize Current State analysis
- Compile data from the Technology Days and focus groups
- Hold workshops with the Project Team and Stakeholders to begin drafting the Vision Statement and Guiding Principles
- Draft a Vision Statement and Guiding Principles