August 1, 2002
To: Ilee Rhimes, Chief Information Officer
From: Cathy Bindewald, PlanIT Project Manager
Subject: PlanIT Project Status for July 2002
- Accomplishments
- Project Activities
- Updated PlanIT Web site
- Held an Executive Sponsor Committee Meeting
- Held a Stakeholder and CIO Advisory Committee Meeting
- Current State Activities
- Circulated the Draft Current State Interim Report to the Project Team for comments
- Shared the Draft with the Stakeholders, CIO Advisory Committees and the Executive Sponsors and requested comments
Posted the appendices to the Draft Report on the PlanIT Web site
- Future State Activities
- Reviewed the draft vision statement and guiding principles with the Project Team and the Stakeholder/ CIO Advisory Committee Members
- Continued to incorporate comments on the Draft Vision Statement and the guiding principles
- Conducted a focus group session with representatives from the Office of Student Affairs
- Gap Analysis and Initiatives Activities
- Reviewed the evaluation criteria and weightings with the Executive Sponsors
- Revised the evaluation criteria and weightings based on the input from the Executive Sponsors
- Began holding team meetings twice per week
- Deliverables Completed:
- Draft Current State Report
- Draft Vision Statement and Guiding Principles
- Administrator Survey
- June status report
- Comments
- Not Applicable
- Problems/Issues/Concerns
- Not Applicable
- Tasks Planned for 08/01/02 through 08/30/02
- Revise Draft Current State Report to incorporate comments
- Continue to revise the Vision Statement and Guiding Principles to incorporate comments
- Meet with the Executive Sponsors
- Work on the development of the Strategic Initiatives