Project Brief
planit logo

Office of the Chief Information Officer
PlanIT> Communications> Project Brief

March 1, 2002

To: Ilee Rhimes, Chief Information Officer

From: Cathy Bindewald, PlanIT Project Manager

Subject: PlanIT Project Status for February 2002

  1. Accomplishments
    1. Project Initiation Activities
      • Prepared Project Templates, Project Plan, Project Kickoff
      • Held weekly meetings with Project Team members to discuss PlanIT approach, the project plan and solicit input from the project functional leads
      • Finalized Executive Sponsor and Stakeholder representation in the project's governance structure
      • Developed a communication plan for the project
      • Developed the PlanIT logo and PlanIT Web site
      • Wrote and placed PlanIT Kickoff article in OnCampus on 2/21 and obtained Lantern coverage
      • Placed paid advertisements in OnCampus and the Lantern on 2/21
      • Kickoff announcements ran in OSUToday and Buckeye News
      • Held two Kickoff Presentations for the Stakeholder Advisory Committee, the CIO Technology Advisory Committees, CIO staff and OIT Leaders, regional campuses attended via IP video
      • Briefed the Provost and Vice Provost on the PlanIT strategy
      • Scheduled the President Cabinet's Executive Stakeholder interview for 3/6/02

    2. Current State Activities
      • Held weekly meetings
      • Mapped out a Current State high-level approach using survey instruments, interviews and questionnaires
      • Initiated the review of existing documentation from previous efforts such as Y2K, the OSU Poll and the End User Access Assessment
      • Began crafting questions for faculty, students, staff, administrators and alumni

    3. Future State Activities
      • Mapped strategy for conducting Technology Days and began to make assignments for the Future State process
      • Decided to conduct five Technology Day sessions on the following topics
        • Advancing Distributed and Distance Education
        • Managing Customer and Student Relationships
        • Managing Data and Knowledge
        • Building Pervasive Computing Environments
        • Supporting High Performance Computing
      • Each session will include a discussion of the enablers (personnel, infrastructure, services and resources) and shapers (campus culture, laws and policies, cost) that affect the topic
      • Began developing a list of prospective individuals to address each topic
      • Began to identify future state focus group representation

    4. Gap Analysis and Initiatives Activities
      • Adapted the Strategic Initiative Assessment Score sheet template to the OSU environment
      • Tested the score sheet with a sample initiative

    5. Deliverables Completed:
      • PlanIT Project Kickoff Power Point Template
      • Microsoft Project Plan
      • Executive Interview Guide
      • Current State High-Level Approach
      • Current State Interview Guide
      • Future State Questions for Current State Evaluation
      • Technology Day presentation subjects
      • Technology Day speaker evaluation forms
      • Technology Initiatives evaluation template
      • Value Framework Template
      • PlanIT Website
      • First PlanIT News article
  2. Tasks Not Accomplished this monthly period, with explanation
  3. - Not Applicable

  4. Problems/ Issues/Concerns
  5. - Not Applicable

  6. Tasks Planned for 03/01/02 through 03/31/02
    • Interview Executive Stakeholders
    • Finalize Current State questions for the survey
    • Initiate survey
    • Finalize the evaluation of previous efforts and gather relevant data
    • Validate data from previous efforts
    • Begin to gather the data not found in documentation from previous efforts
    • Finalize logistics for the Technology Days presenters, dates, times, places, etc
    • Complete assignments for Future State Tasks
    • Finalize Future State focus group representation
    • Finalize Strategic Initiative Assessment Score sheet criteria and values